VENETIA UNDERGROUND PROJECT (VUP)

 

Logo

Phase: Execution
Status: Ongoing


The Venetia Mine is located on the farm Venetia 103MS, Rugen 105MS, Krone 104MS, Drumsheugh 99MS and is situated about 80km west of Musina and 40km north-east of Alldays in the Limpopo Province of South Africa. The mine was opened in 1992, with a sampling programme has taken place in 1969, and the viable kimberlite pipes were discovered in 1980. The Venetia Deposit consists of 12 kimberlite pipes. The depletion of the opencast ore Resources was reached at a final pit cut depth of 600m. The open-pit mining operations reached their end of life in December 2022 after 30 years of production. The mine transitioned from an open-pit to an underground operation which will extend the Life of the Mine (LoM) by 23 years, with operations continuing until 2046. The construction of the mine is divided into three construction areas, Top of Mine (TOM) levels 46L to 54L, Bottom of Mine (BOM) levels 56L to 100L and Surface. The TOM is the four production levels 46L to 54L, BOM is 56L to 100L which will be mined through the shaft complex. Construction will continue at BOM, TOM started production in July 2023 and will mine 4Mtpa Run of Mine (RoM) for the first 4 years after which BOM will start production, and nameplate capacity will be reached in 2026.

 

Construction start:   13 Oct 2013

Production start:  1 Jan 2022

Region:  Southern Africa

Country: South Africa

Province: Limpopo

City:  Musina

GPS coordinates:  22°27'00.0" S, 29°19'00.0" E

Capital value:   ZAR 23 432 500 000.00

Last Update:  31 Oct 2023

Mineral:  Diamonds

Plant Type:  Expansion

Mining Type:  Underground


Method:

Underground Mining. The underground mining method will be done through block caving which is an underground hard rock mining method that involves undermining an ore body, allowing it to progressively collapse under its own weight. The underground mine will comprise two vertical shafts to a depth of about 1,040m. Shaft sinking used a new Canadian method that is designed for all activities in the shaft sinking production cycle and this, the Canadian Shaft Sinking Model, has improved mining safety.

The underground operation will exploit the resources to a depth of approximately 1 000 m, extending the Life of Mine to between 2044 and 2046. This will comprise of two vertical shafts to the depth of about 1 040 m. Shaft sinking will use a new Canadian method which is considered to be safer than the traditional South African method and will commence in the middle of 2014. The Canadian shaft sinking model is designed for all activities in the shaft sinking production cycle. The Venetia Deposit consists of 12 kimberlite pipes and the Company is mining two of the largest in a single open-pit operation.


Process:

The Processing Plant will treat the underground ore when production moves underground. The plant was constructed to process 4,8Mt of ore per annum. They improved the process to increase the throughput to 6Mtpa (million tonnes per annum), along with the K1 and K2 Pipes giving the choice to possibly mine 8Mt per annum, which will require an added stream to the existing plant. The kimberlite ore is stockpiled close to the plant where it is crushed and processed to recover the diamonds. A coarse Resource tailings dump is generated along with a fine residue disposal facility for the kimberlite fines. The production process is a physical extraction process and not a chemical one. The haul trucks will tram to the surface through the pit ramp followed by a Top of Mine Crusher that will crush the ore for hosting with the production shaft. The ore of the bottom crushers will be loaded into ore passes and transferred to the crusher using automated trucks.


Project Commentary:

October

  • De Beers Group has confirmed that Venetia Underground has delivered its first production from the Top of Mine (TOM).
  • The construction of the underground operation is now 70% complete with construction and production ramp-up continuing.
  • Bottom of Mine (BOM) will reach nameplate capacity production during 2026. Bottom of Mine (BOM) will reach nameplate capacity production during 2026.
  • 3
  • The open-pit ceased production during December 2022 after 30 years of production.

June

  • De Beers confirmed that they are in the pre-production phase with most of the construction activity taking place at the Top of Mine (TOM) from 46L to 56L.
  • The first production will be from the 46L rim tunnel which is above KO1 open-pit operation and is estimated to produce 6Mtpa for the first four years.
  • Shafts of 1,000m will be used to gain access to the mine and orebodies.
  • The mine will also make use of Boston Dynamics’ Agile Mobile Robot named Spot, which will be sent in after an area has been blasted to check ground conditions and provide analytics and data with potential risks.

March

  • De Beers confirmed that they will achieve operational readiness and first production during 2023.
  • A trackless fleet will be supportin the underground operation.
  • The first water control door has been completed which has a steel frame of 8m high, 8m wide and 1m thick is secured by 234 anchors of 40mm, containing 60 tonnes of steel. A total of 80 cubic metres (m3) of concrete was used to seal the doors and the surrounding area.
  • CC Crane Hire provided cranes to the Venetia Underground Project, Deswik Mining Consultants provided the software solutions, Master Drilling (Pty) Ltd completed Raisebore Drilling and BMH Africa assisted with a skills development programme.

October

  • Standard Bank has provided a debt funding package of 4 Billion Rand to De Beers to fund the Venetia Diamond Mine's underground project.
  • The Venetia Mine has created over 3,000 jobs which included 1,700 of the local community.

July

  • Concor Construction advised that they will complete the construction of a new Pollution Control Dam 3 (PCD3) in 17 months' time, which will be the main containment facility in the Storm Water Management Project (SWMP).
  • aximum height of 13m, which will be able to contain over a million cubic metres of water.
  • Concor will ensure that the construction of the PCD will not impact the Venetia Underground Project, they will construct a security fence, and upgrade the existing road to the temporary site facility.
  • The construction of a pump station and dam spillways, and a 2,5km return waterpipeline to the mine’s processing plant.

May

  • De Beers Consolidated Mines Ltd confirmed that Venetia Mine produced 1,161 Million carats during Q1 of 2021 compared to 751 Million carats during Q1 of 2020.
  • The Company's overall production is at 95% of its normal capacity and is meeting the customer demand during Q1 of 2021

July

  • De Beers overall diamond production decreased by 8% to 7,9 Million carats.
  • De Beers Consolidated Mine’s (DBCM) production decreased by 65% to 0,4 Million carats due to the lower production from Venetia’s transition from open-pit to underground
  • Rough diamond sales totaled 7,5 Million carats compared to 8,8 Million carats during Q1 of 2018.

August

  • De Beers confirmed an overall rough diamond production of 9,0 Million carats which was an increase of 3%
  • Rough diamond sales during Q2 of 2018 were 10,2 Million carats.
  • Production decreased by 28% to 1,0 Million carats due to a fatality at the Venetia Mine and production being suspended.

August

  • De Beers Consolidated Mines reported that rough diamond production for Q2 of 2017 increased by 36% to 8.7 Mc (million carats), in line with the production projection for 2017.
  • Production at De Beers Consolidated Mines increased 71% to 1.4 Mc. This was due to higher grades at Venetia.
  • Rough diamond sales during Q2 of 2017 were 5.4 Mc.
  • Alta van Dyk Environmental Consultants CC (AVDEC) was appointed as an independent consultant to compile a Social Impact Assessment as part of the Environmental Impact Assessment for the temporary accommodation facility.
  • The accommodation facility will house 800 to 1 000 employees for a period of 6 years and will consist of brick, mortar and prefabricated structures. Facilities will include a substation, water treatment plant, medical centre, workshop, laundry, kitchen, dining area, recreation facility, gymnasium, swimming pool, soccer field, change rooms and ablution facilities.

February

  • De Beers reported rough diamond production for Q4 of 2016 increased by 10% to 7.8 Mc compared to Q4 of 2015.
  • Production at De Beers Consolidated Mines decreased to 1.4 Mc. This was due to the sale of the Kimberley Mines during Q1 of 2016.
  • An increase of 18% at Venetia was due to the processing of higher grades.
  • Rough diamond sales during Q4 of 2016 doubled to 8 Mc compared to Q4 of 2015.
  • Sales of rough diamonds increased by 55% to 32 Mc during 2016.
  • The construction of the Venetia Underground Project is still progressing and is scheduled to begin production in 2022 with full production expected in 2025.

December

  • De Beers reported that the construction of the Venetia Underground Project is still progressing with the decline advancing to 1 550 m together with progress being made with the shaft sinking.
  • The decline from surface is 2 km in length as it develops down to 540 m. Development of the decline is at a rate of 140 m a month.
  • Headgears of the two shafts have been constructed and are advancing at a rate of 66 m/month to reach a depth of 1 080 m below the surface.
  • De Beers and its holding company Anglo American has reappointed Worley Parsons RSA under a new contract with amendments to the project execution synopsis which is in line with Anglo American's new model. The project scope will provide for a techno-economic underground mining and infrastructure solutions.
  • Worley Parsons responsibility as Engineering Procurement Construction Management (EPCM) will consist of project management, project controls, quality management.
  • De Beers reported an increase of 4% to 6.3 Mc in production compared to Q3 of 2015.

September

  • Anglo American is the holding company of De Beers and Anglo American has 85% shareholding in De Beers. The Venetia Mine and Venetia Underground Project is 100% owned by De Beers.
  • De Beers announced that the underground development is on schedule and might start production before 2022.
  • The Venetia Underground Project will employ 6 000 people during mining operations, including 2 000 in the construction sector by 2019.
  • The vertical shaft sinking operations are advancing with all groundwork such as the surface facilities, headgears and terraces being established. Genrec Engineering Pty Ltd (part of Murray and Roberts) who was the fabrication and erection contractor for the headgears at the mine work has completed their work and they are no longer on site.
  • The sinking of the production shaft is one-quarter complete reaching a depth of 250 m and the service shaft reaching a depth of 150 m. The 7.5 km decline access is being developed at a rate of 130 m a month with a decline of 2.5 km already reached, declining 9° to a depth of 1 000 m.
  • Ground and water handling systems have not been awarded to any contractors.
  • De Beers will focus on ensuring the decline reaches 540 m below surface within the next 2 years, with all shaft sinking operations completed by 2018.
  • Rigid Dump Trucks (RDT) transport in excess of 40 million tonnes of material per year. To retrieve the diamonds they will haul out 91.4 million tonnes of material per year which will contain with every tonne of rock, dust, water, red earth and kimberlite ore winched up in the vertical production shaft, a projected 0.765 carats of diamonds.
  • Underground mining will reduce the amount of waste the trucks are hauling from the open-pit. As of now they are mining 40 to 50 million tonnes of waste per year. Once the underground operation has commenced, this will be reduced by half.
  • Venetia uses 7 of their own Joy Global large diameter drill rigs for blasting, and African Explosives Ltd (AEL) operates a further 3 Pit Viper big diameter drilling rigs. Subcontractors drill in areas where working space is constrained of drilling is close to the edges of the pit. There are 12 small diameter drill rigs, the majority of which are owned by Atlas Copco.
  • Blasted fragments, rock and ore is shoveled by seven 600 tonne CAT 660 shovels into 42 large RDT bins.
  • During the rainy season 440 mm of water accumulated at the bottom of the pit, which will take five months to dewater, there is 1,2 Million cubic metres of water in the bottom of the pit which is being pumped out at 300 cubic metres per hour and used in the processing plant.
  • SRK Vancouver constructed a 3D Model that forecasted the dominant structural geometries at depths, below the pit.
  • Speedspace has provided the mine with 2 730 m2 of prefabricated modular buildings.

June

  • De Beers Consolidated Mines (DBCM) reported that there has been steady progress and the Venetia Underground Mine (VUP) is projected to meet the 2022 target date for completion.
  • In Q1 2016, the production decreased by 12% to 932 000 carats, due to the finalisation of the sale of the Kimberley Mines.
  • Anglo American projected that the estimated $2.1 billion VUP will extend the present Life of Mine (LoM) to 2046.
  • The 2 vertical shafts (each 7 m in diameter) are being sunk to a depth of 1 080 m, an operation that will take until 2028, and Murray & Roberts Cementation is doing the shaft sinking for the VUP.
  • The initial modules (for shaft sink) of the production shaft were pre-erected on the ground, with the production shaft headgear about 86 m in height and the crane lifted all of those modules.
  • The pre-sink gantry is a necessity to get down to about 60 m (stage 4 level, about 20 m in length), before implementing the main sinking structures and this is a multi-deck platform on which the workers can move.
  • The kibble holes (through which two 10 tonne skips) are used to bring out the blasted material and depending on the blast, it takes about 40 skip lifts to get the blast muck cleaned out.
  • This is a manual process of drilling and blasting the shaft bottom (3 m a blast, 3 m a day, every day) for 2 years, until they can reach about 1 080 m.
  • The production shaft and service shafts are presently at about 14 0m to 145 m and 100 m deep respectively (about 3 months behind schedule) and will ultimately reach a depth of 1 000 m.
  • The construction of the underground tunnels and infrastructure will take place from the shafts, with the decline ramp reaching a depth of about 1 km, providing access to the initial ore bodies.
  • The drill rig unit (attached to the winder) is lowered down the shaft, where it is then hung on the stage.
  • There are 3 drill rigs on each 1 of these drilling units and it drills the shaft bottom, drilling about 180 holes for every blast at about 3 m deep.
  • There are 2 drilling units (1 is executable, the other is a spare) and after drilling the bottom and blasting the bottom, there is a mucking cycle during which 2 vertical shaft muckers (fixed on the stage) are lowered down the shaft, mucking the shaft bottom and filling the kibbles.
  • The kibbles are winched up the shaft, tipped on surface into 2 chutes and the waste is trucked to the dump.
  • When the mucking is complete, it then goes through a blow over cycle (using compressed air) to clean the shaft bottom before drilling can re-commence.
  • During construction, the removal of rock to build shafts, tunnels and infrastructure will engender enough rock to pave a road from Musina (Limpopo) to Cape Town (Western Cape) and back, while generating the revenue required for DBCM to fund the mining investment, without taking on bank debt.
  • DBCM last suffered a fatality in 2008 and this drives the dedicated approach to the integration of surface and underground mine (under construction), beneath our operating open-pit.
  • Mining of the 3 open-pit kimberlites will ultimately be phased out, with K1 taking the mine through to 2022 (underground mining starting at about 50m below point where production above ground stopped), K2 closing off at the end of 2016 and K3 projected to end in 2017
  • The working cost of underground mining is lower than surface mining, producing lower waste and a lower environmental impact.
  • As part of the VUP, houses are being built (nearby Musina) to accommodate workers, support will be given to improve roads, about 1 500 jobs already created for local community and another 500 to be conscripted when major underground work commences.

March

  • Anglo American reported that the Venetia Underground Project (VUP) is projected to treat about 132 Mt of material containing an estimated 94 Mc.
  • The estimates are scheduled tonnes and carats as per the Life of Mine (LoM) Plan (approved in 2015), with the Inferred Resources (39.5 Mt) constituting 24% (22.4 Mc) of the estimated carats.
  • De Beers Consolidated Mines (DBCM) cut their costs of production from $111/carat in 2014 to $101/carat in 2016.
  • Between 2015 and 2017, DBCM’s capital expenditure is projected to decline by around $200 million to $500 million, mainly due to the completion of the mine development in Canada.
  • DBCM is capping their exploration budget for 2015 and 2016 at $35 million and limiting exploration activity to Botswana, South Africa and Canada.
  • The 2016 Production Programme for Debswana, De Beers Joint Venture (JV) with the Botswana Government has been revised to 20 Mc, which will still account for more than 70% of DBCM’s total production.
  • At DBCM, the total diamond production for Q4 2015 decreased 16% to 7.1 Mc.
  • The Venetia production declined, due to the reduction in tonnes treated and the offset by increased production at Kimberley with a consistent decision to reduce production in line with trading conditions.
  • The Q4 production increased 17% compared to Q3 2015, due to the improved grade at Orapa and as a result of an annual planned 6 day plant shutdown at Venetia in Q3 2015.
  • DBCM is maintaining a flexible approach to production and have the capacity to increase the production via their tailings operations at Venetia and Jwaneng.
  • The construction of the Venetia Underground Mine continues to progress, with the decline advanced to more than 1 100 m and the VUP is 21% complete.
  • The underground operation is projected to become the key source of ore at Venetia from late 2022.
  • There will be a reduction in employees with more than 1 500 job losses, across Canada and Sweden, with the South African Plant being restructured.
  • In February 2016, the National Union of Mineworkers (NUM) issued a statement questioning the rationale and process for the restructuring undertaken at DBCM’s Venetia Mine and the notices have been issued to 189 employees.
  • The details and rationale for issuing S189s at Venetia have been communicated to NUM prior to issuing the notice.
  • DBCM’s Venetia Mine employ 1 534 of the 2 236 employees and there are 189 positions affected, of which 152 relate to the Venetia Mine, with 68 positions which may be reduced without retrenchments or natural attrition from retirements or redeployment of employees.
  • The remaining 121 positions will be focussed at the Corporate Office in Kimberley, the Corporate Office in Johannesburg, the Venetia Mine and the VUP.
  • DBCM and Venetia Mine have an excellent Employment Equity Record and the potential retrenchments are a last resort.

Subscribe for full commentary.

Subscribe for full commentary.

Subscribe for full commentary.

Subscribe for full commentary.

Subscribe for full commentary.

Subscribe for full commentary.

Subscribe for full commentary.


Mine Owners:

DE BEERS CONSOLIDATED MINES LTD – 100%

Designation Name Tel. Fax Email
Internal Communications Manager xxxxxxxxxx +27 xx xxx xxxx   xxxx.xxxxxxx@angloamerican.com
Chairman and Non-Executive Director xxxxxxxxxx +27 xx xxx xxxx +27 xx xxx xxxx xxxx.xxxxxxx@angloamerican.com
Financial Manager xxxxxxxxxx +27 xx xxx xxxx +27 xx xxx xxxx xxxx.xxxxxxx@angloamerican.com
Group Chief Executive Officer xxxxxxxxxx +27 xx xxx xxxx +27 xx xxx xxxx xxxx.xxxxxxx@angloamerican.com
Chief Financial Officer xxxxxxxxxx +27 xx xxx xxxx   xxxx.xxxxxxx@angloamerican.com
Executive Head, Strategy and Corporate Affairs xxxxxxxxxx +1 xxx xxx xxxx   xxxx.xxxxxxx@angloamerican.com
Senior Engineering Manager xxxxxxxxxx +27 xx xxx xxxx +27 xx xxx xxxx xxxx.xxxxxxx@angloamerican.com
Project Planner xxxxxxxxxx +27 xx xxx xxxx +27 xx xxx xxxx xxxx.xxxxxxx@angloamerican.com
Employee Relations Manager xxxxxxxxxx +27 xx xxx xxxx +27 xx xxx xxxx xxxx.xxxxxxx@angloamerican.com
Chief Executive Officer – De Beers Consolidated Mines xxxxxxxxxx +27 xx xxx xxxx +27 xx xxx xxxx xxxx.xxxxxxx@angloamerican.com
General Manager xxxxxxxxxx +27 xx xxx xxxx +27 xx xxx xxxx xxxx.xxxxxxx@angloamerican.com

Project Engineers:

LYCOPODIUM ADP (PTY) LTD (ADP PROJECTS) – Conceptual Mining Study

Designation Name Tel. Fax Email
Director xxx xxxxx +27 xx xxx xxxx +27 xx xxx xxxx xxx.xxxxx@lycopodiumadp.co.za

MURRAY & ROBERTS CEMENTATION CANADA INC – Training & Implementation

Designation Name Tel. Fax Email
President xxx xxxxx +27 xx xxx xxxx +27 xx xxx xxxx xxxx@cementation.ca

MURRAY & ROBERTS CEMENTATION – Principle Engineer and Funding

Designation Name Tel. Fax Email
Business Development Director xxx xxxxx +27 xx xxx xxxx +27 xx xxx xxxx xxxx.xxxxx@murrob.com
Group Chief Executive Officer xxx xxxxx +27 xx xxx xxxx +27 xx xxx xxxx xxxx.xxxxx@murrob.com

WORLEYPARSONS RSA PTY LTD (TWP) – EPCM Engineer

Designation Name Tel. Fax Email
HOD Construction Management xxx xxxxx +27 xx xxx xxxx +27 xx xxx xxxx xxxx.xxxxx@worleyparsons.com
Project Manager xxx xxxxx +27 xx xxx xxxx +27 xx xxx xxxx xxxx.xxxxx@worleyparsons.com

CONCOR CONSTRUCTION (MURRAY & ROBERTS INFRASTRUCTURE) (RESOURCES & INDUSTRIAL - CONCOR ENGINEERING)

Designation Name Tel. Fax Email
Civil Estimator Senior xxx xxxxx +27 xx xxx xxxx +27 xx xxx xxxx xxxx.xxxxx@basilread.co.za

SRK CONSULTING (VANCOUVER) – Integrating Structural Geology and Geotechnics

Designation Name Tel. Fax Email
Senior Consultant xxx xxxxx +27 xx xxx xxxx   xxxx.xxxxxxxx@srk.com

SRK CONSULTING (VANCOUVER) – Integrating Structural Geology and Geotechnics

Designation Name Tel. Fax Email
Head of Venetia Underground Project (VUP) xxxxxxxxxx +27 xx xxx xxxx +27 xx xxx xxxx xxxxxxx@debeersgroup.com

Project Suppliers:

AFRICA EXPLOSIVES LTD (AEL) – (HEAD OFFICE) Explosives
ENVIRONMENTAL MANAGEMENT SOUTHERN AFRICA (PTY) LTD – CAPE TOWN Scoping and Environmental Impact Assessment Process (EIA), Waste Management Licence, (WML) and Public Participation Process (PPP)
ESKOM Power Supply and High-Voltage Line
S.M.E.I. PROJECTS (PTY) LTD Structural, Mechanical, Plate Work and Piping
SANDVIK MINING AND CONSTRUCTION Underground Equipment (Underground Automation)
ATLAS COPCO Drill Rig
DEPARTMENT OF MINERAL RESOURCES (DMR) (RSA) Approvals
AURECON SOUTH AFRICA (PTY) LTD (QUOIN) Consulting for Feasibility Study
GENREC ENGINEERING (PTY) LTD (PART OF MURRAY & ROBERTS) Headgear
CONSOLIDATED POWER PROJECTS (PTY) LTD (CONCO) Power Supply
SSG CONSULTING Project management System (KEY360)
QUANTEC GEOSCIENCE Geophysical Surveys
MINISTRY OF MINES AND ENERGY (NAMIBIA) Sales Agreement
BP MASANA Diesel Requirements
LIMPOPO NATURE RESERVE, ENVIRONMENT AND TOURISM Environmental Management Plan
BARLOWORLD EQUIPMENT (CORPORATE OFFICE) Earth Moving Equipment
SPEEDSPACE Prefabricated Modular Buildings
REINFORCED EARTH (PTY) LTD Wingwalls
ALTA VAN DYK ENVIRONMENTAL CONSULTANTS CC (AVDEC) Social Impact Assessment & Environmental Impact Assessment for Temporary Accomodation Facility